Here's how Baptist Jax will remain completely operational during major renovation

Here's how Baptist Jax will remain completely operational during major renovation

Baptist Health Jacksonville is investing $190 million to build a four-story, 123,000-square-foot emergency tower on its flagship campus, scheduled for completion in 2029. Designed by Hoefer Welker, the project faces complex challenges, as the hospital must remain fully operational during construction.

To address this, the team will take a phased approach with six to seven major stages, ensuring no loss of functional space. Erik Higgins, Senior Project Manager, compares the process to a "shell game," carefully sequencing new construction before decommissioning old areas. Additional hurdles include maintaining patient safety amidst noise, dust, and heavy equipment while navigating a site with critical infrastructure, like water and communication lines, and a construction history dating back to the 1960s.

Learn more here >>>

Transformational Bank of America Plaza Redevelopment Gets Boost from City

Transformational Bank of America Plaza Redevelopment Gets Boost from City

D CEO Magazine recently featured the transformational redevelopment of Bank of America Plaza, highlighting the City of Dallas’ approval and financial...

Read More
Best Higher Ed/Research: Texas Christian University, Burnett School of Medicine – Arnold Hall

Best Higher Ed/Research: Texas Christian University, Burnett School of Medicine – Arnold Hall

ENR Texas & Louisiana has recognized the TCU Burnett School of Medicine as the Best Higher Education/Research Project of 2025. Located in Fort...

Read More
Designer Roundtable - Environments That Heal

Designer Roundtable - Environments That Heal

Hoefer Welker’s Director of Interiors, Tiffany Kalloor, was featured in Healthcare Construction + Operations magazine’s Designer Roundtable:...

Read More